Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie

How soon does blocklaying start after ..?

Options
  • 05-07-2006 4:41pm
    #1
    Registered Users Posts: 880 ✭✭✭


    after the raft foundation goes in ?

    Let's assume raft installed during this fine patch of weather
    (not sure if average day temperature or humidity matters).

    Also.. in terms of the number of courses of blocks which
    can be laid in the eairly stages of the build. 4 or 6 rows
    of blocks maximum? less/more ?

    Are the rules of thumb fairly straightforward on this or is
    it complex .. depending on the type of soil the foundations
    were laid in, the footprint size of house, raft versus strip,etc?

    -ifc


Comments

  • Registered Users Posts: 576 ✭✭✭ifah


    my blocklayer started about 3 days later - that was back in february - he had said he would be happy starting the next day.
    he built up about 6 courses of block at a time.


  • Registered Users Posts: 880 ✭✭✭ifconfig


    Thanks Ifah - that checks out with my experience with our build.
    Raft poured on a Friday.. left over the weekend. Blocklaying started
    Tuesday of following week. Six courses of blocks was what the
    foreman told me they were putting up.

    I just wanted to check with the collective intelligensia on the
    boards that there wasn't anything out of the ordinary about
    the build. It is great to see it getting going.

    In terms of more critical times in the build when there should
    be a lengthy pause. What do most feel is the correct amount
    of time to pause works to allow plaster to dry (at plastering
    first fix, for example...)
    While I'd love to be in our new house by Christmas I'd still
    like to know that due attention has been given to giving
    good allowance for drying out , settling, etc ?

    -ifc


  • Moderators, Home & Garden Moderators, Regional Midwest Moderators, Regional West Moderators Posts: 16,724 Mod ✭✭✭✭yop


    I wud expect the same after say 5 days they should start.
    Max he should be building is 6 or 7 rows per day.


  • Registered Users Posts: 680 ✭✭✭Salmon


    Folks,

    Anyone have any advice on how soon after the footings are laid you should fill and whack the hardcore? The footings on my house will be finished on wed and the guy doing my foundations wants to fill and whack on thursday! Is this a little too soon, does anyone have any experience of this?


  • Closed Accounts Posts: 21 the brickie


    at this time of the year you would want to leave at least 3-4 days after
    finishing the footings before backfilling.especially as we had such frost last
    night the mortar would not have gone off fully yet.sounds like someone
    wants money before the christmas breakup


  • Advertisement
  • Registered Users Posts: 680 ✭✭✭Salmon


    Yeah, I think your right! I held him off until next thursday! Just out of interest what should I consider to be a good price for laying 2500 blocks in the footings, 9000 approx in the house and putting in the foundation and finished floors? I got a price from one fella to do it and was wondering what the going rate would be?


  • Closed Accounts Posts: 21 the brickie


    salmon
    like everything it depends where you are ,around the limerick area
    you would expect to pay around €20000 vat inclusive probably plus or minus
    15%for dublin and other areas.obviously if johnney cash is involved in the
    building it will be much less.


Advertisement