new connection to ESB

  • 11-11-2009 1:15pm
    #1
    Registered Users Posts: 288 ✭✭


    Hi, just applying to get ESB connection to site about to start building in next couple of months. On the form it asks for kW for the immersion & the oil boiler - does anyone have any idea what these would be? we were just gonna go for the std 12kVA as we dont have a heat pump but would we better going for 16kVA just in case? we havent finalised contractor yet so dont have an electrican to ask!
    Thanks.


Comments

  • Closed Accounts Posts: 1,712 ✭✭✭davelerave


    You get extra capacity with the 16Kva(80amp).The supply is better quality in rural areas esp.(regards voltage drop).I would get it anyway if possible.


  • Registered Users, Registered Users 2 Posts: 19,340 CMod ✭✭✭✭Davy


    The enhanced supply costs an extra €600 in a standard connection. Its not going to do you any harm but the normal 12kva supply would most likely do you.