Contractor RFIs

  • 07-02-2013 5:47pm
    #1
    Registered Users Posts: 66 ✭✭


    Hi,

    Can anyone advise on a reasonable time frame for responding to a request for further information from a contractor to a member of the design team? Or where guidance can be sought?

    Cheers


Comments

  • Moderators, Home & Garden Moderators Posts: 10,145 Mod ✭✭✭✭BryanF


    Ray Dow wrote: »
    Hi,

    Can anyone advise on a reasonable time frame for responding to a request for further information from a contractor to a member of the design team? Or where guidance can be sought?

    Cheers
    Ill bow to a Qs on this but, wouldn't A week seem more than reasonable? or if there's an issue the item could be made a pc. the main thing is you inform everyone tendering to expect an AI and extend the return date accordingly


  • Registered Users, Registered Users 2 Posts: 10,556 ✭✭✭✭DvB


    Is this a tender stage RFI or a construction stage RFI with a contractor already assigned?

    If already on site, in my experience the RFI is normally issued with a reasonable date indicated for the information to be returned in order to not upset the programme. If no date indicated it would depend & would probably be project specific depending on the scope of works.
    "I will honour Christmas in my heart, and try to keep it all the year" - Charles Dickens




  • Registered Users Posts: 66 ✭✭Ray Dow


    Construction stage. A Letter of Intent is being sent to the contractor and we wish to include a note on RFIs.


  • Registered Users Posts: 31 alibaba2


    what kind of contract?


  • Registered Users Posts: 66 ✭✭Ray Dow


    RIAI with Quantities