Dormer bungalow, cost of upstairs build

Options
  • 11-01-2016 12:13am
    #1
    Registered Users Posts: 17


    Hi Just wondering if anyone has any feedback or info. I received planning for a dormer bungalow. Downstairs is 240 sq m and upstairs is 70 sq m. I'm just wondering in terms of cost of build, what's the difference in price of doing the upstairs rooms. I have been told €1000 per square m for downstairs and 60% of that for upstairs area because the roof etc will be there anyway so doesn't cost as much. Is that accurate? I know prices depend on specs but roughly. I'm thinking of just doing downstairs and leaving upstairs, not sure yet.


Comments

  • Moderators, Society & Culture Moderators Posts: 39,458 Mod ✭✭✭✭Gumbo


    Hi Just wondering if anyone has any feedback or info. I received planning for a dormer bungalow. Downstairs is 240 sq m and upstairs is 70 sq m. I'm just wondering in terms of cost of build, what's the difference in price of doing the upstairs rooms. I have been told €1000 per square m for downstairs and 60% of that for upstairs area because the roof etc will be there anyway so doesn't cost as much. Is that accurate? I know prices depend on specs but roughly. I'm thinking of just doing downstairs and leaving upstairs, not sure yet.

    Where are you located?
    Depending on location, €1000 sounds cheap.

    Also you need to think of part L compliance and how you create your insulation envelope now, so that you don't destroy it in the future creating the upstairs space.


  • Registered Users Posts: 12,467 ✭✭✭✭Calahonda52


    Thats a big gaff :)
    Too cheap in my view:
    have a look here https://www.scsi.ie/advice/house_rebuilding_calculator


    As KC says, do the entire envelope for A/T, insulation, ensuite plumbing and extraction etc etc now.

    “I can’t pay my staff or mortgage with instagram likes”.



  • Registered Users Posts: 17 hellsbells83


    I'm in Laois don't know if that makes a difference to the cost. Will probably do envelope for part L so that entire house can be used. But we don't need to do the upstairs, might never I suppose it's essentially a bungalow with an option of upstairs.