Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi all! We have been experiencing an issue on site where threads have been missing the latest postings. The platform host Vanilla are working on this issue. A workaround that has been used by some is to navigate back from 1 to 10+ pages to re-sync the thread and this will then show the latest posts. Thanks, Mike.
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Opting out of Designed Certifier(DC) &Assigned Certifier(AC) Process???

  • 31-03-2016 9:25pm
    #1
    Registered Users, Registered Users 2 Posts: 1,000 ✭✭✭


    I read that the govt have laxed on their insistence to abide by above and have given people an option to opt out of this process. Will be looking to self build in next year and wondering will I be able to avoid this requirement. Will be looking for mortgage and wondering if all or some banks insist on abiding by this legislation. I know that failure to abide by this could have knock on effects if selling the house but this is not something I will be planning.

    Interested in hearing peoples thoughts on this.


Comments

  • Moderators, Society & Culture Moderators Posts: 39,802 Mod ✭✭✭✭Gumbo


    SI365 of 2015 allows this.

    Some banks are insisting on an Assigned Certifier been appointed, others are insisting on a registered professional been appointed such as CIOB, Non Chartered Engineer etc

    It will depend on your banks requirements, but subject to funding, you can indeed opt out on a one off self build.


  • Registered Users, Registered Users 2 Posts: 270 ✭✭RORY O CONNOR


    If you are borrowing from a bank to pay for the build it is likely the funds will be released in stages. Most of the banks these days require the payments to be certified as having been completed to building regs. Some have sections that need to be filled in referring to the commencement notice dates and the planning ref nos also filled in.

    The banks typically insist that you use a suitably qualified and professionally registered individual for this with PI insurance typically of €500,000 at a minimum. As the time involved and the responsibility is pretty much the same you may as well op it as opt out because some of the fees being charged for this service are typically about the same-depending on who you use of course!

    The banks also typically want final certification for compliance with the planning permission as well as the building regs before the final payment is released down so again if someone doing this for you its pretty much the same overall as having an AC on board.

    There are bound to be some on here who will absolutely disagree and that's fine-its simply an opinion.