Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie

When will cabinets on the west side of Clonakilty be enabled?

Options
  • 17-08-2016 10:26pm
    #1
    Registered Users Posts: 57 ✭✭


    Could you please let me know when the 2 cabinets on the west side of Clonakilty will be fiber enabled, on one of your maps its says within 1 year and on another of your maps its says that work has commenced, see attached screenshots..

    Thanks in advance


Comments

  • Closed Accounts Posts: 2,797 ✭✭✭Eir: Pamela


    Dotts wrote: »
    Could you please let me know when the 2 cabinets on the west side of Clonakilty will be fiber enabled, on one of your maps its says within 1 year and on another of your maps its says that work has commenced, see attached screenshots..

    Thanks in advance

    Hi  Dotts,




    Thanks for getting in touch. :)

    I have checked this on our latest deployment plan and both cabinets are in the completion stage,  the estimated date for first Live Fibre Services from these cabinets is Autumn/ Winter 2016.

    -Pamela


  • Registered Users Posts: 57 ✭✭Dotts


    Hi  Dotts,




    Thanks for getting in touch. :)



    I have checked this on our latest deployment plan and both cabinets are in the completion stage,  the estimated date for first Live Fibre Services from these cabinets is Autumn/ Winter 2016.

    -Pamela

    Any idea when or if these cabinets will ever be live it's a year over your prediction date, How long is the completion stage in all fairness.

    Thanks in advance

    Dave


  • Closed Accounts Posts: 1,508 ✭✭✭eir: Adam


    Dotts wrote: »
    Hi  Dotts,




    Thanks for getting in touch. :)



    I have checked this on our latest deployment plan and both cabinets are in the completion stage,  the estimated date for first Live Fibre Services from these cabinets is Autumn/ Winter 2016.

    -Pamela

    Any idea when or if these cabinets will ever be live it's a year over your prediction date, How long is the completion stage in all fairness.

    Thanks in advance

    Dave
    Hi Dotts, 

    I've checked this and the cabinet seems to be live. Feel free to PM me your details and I'll clarify this for you. 

    Thanks 

    Adam 


  • Registered Users Posts: 6 minlan


    Hi eir people what's the delay with these cabinets (cyw1_001 and cyw1_e01)? They've been 'build commenced- completion work in progress' for over a year now on the rollout map and the completion estimate has been pushed back every 6 months for what seems like forever.


  • Closed Accounts Posts: 2,136 ✭✭✭eir: Tracey


    minlan wrote: »
    Hi eir people what's the delay with these cabinets (cyw1_001 and cyw1_e01)? They've been 'build commenced- completion work in progress' for over a year now on the rollout map and the completion estimate has been pushed back every 6 months for what seems like forever.
    Hi minlan, 

    I've checked these cabinets for you on our current rollout file and they are due to be activated within the next 6-9 months. They have not been commissioned yet which is the final stage of activation, and this can take this timeframe. 

    Thanks

    Tracey 


  • Advertisement
Advertisement