Payment schedule

Options
  • 14-02-2019 4:12pm
    #1
    Registered Users Posts: 162 ✭✭


    What is "usual" schedule of payments for one off builds using a main contractor?


Comments

  • Registered Users Posts: 1,174 ✭✭✭kieran.


    It depends on many factors but main ones would be
    • subfloor level,
    • wallplate level,
    • sealed structure( roof on windows in),
    • first fix,
    • second fix,
    • practical completion
    • final retention release


  • Registered Users Posts: 162 ✭✭moldy_sea


    Thanks for that. Would the amount to be paid reflect the cost of each of those stages or is the total divided by the number of stages?


  • Registered Users Posts: 1,174 ✭✭✭kieran.


    The amount to be paid reflects the value of work done of each of those stages, generally its work done and materials on-site (minus retention) or milestone payments at agreed lump sum amounts. Your Arch/Eng should advise you on this.