Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi all! We have been experiencing an issue on site where threads have been missing the latest postings. The platform host Vanilla are working on this issue. A workaround that has been used by some is to navigate back from 1 to 10+ pages to re-sync the thread and this will then show the latest posts. Thanks, Mike.
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

photovoltaic (PV) and feeding into grid

  • 07-05-2020 2:13pm
    #1
    Registered Users Posts: 68 ✭✭


    What are the plans and time frame for electric Ireland taking PV generated electricity from domestic households and exporting to the grid?


Comments

  • Closed Accounts Posts: 1,178 ✭✭✭Electric Ireland: Una


    Hi Arklow10,

    There is currently a pilot scheme in effect - we must advise however that it is not open to new members as of 2014 (the link includes information in relation to ESB Networks also).

    Kind regards,
    Una


  • Registered Users Posts: 8 roryhogan


    Hi, Una. 
    I know the current pilot scheme is closed since 2014.
    , but I want to know when is it opening up again? 
    Under EU regulations all demestic meters have to be 2 way by January 2021.
    Is there any update on this meter replacement? 
    Can I request that my meter is put on a "to do now" list as I am wasting money by giving it to the grid for free.
    Kindest regards. 
    Rory
    Dublin 11


  • Closed Accounts Posts: 1,178 ✭✭✭Electric Ireland: Una


    roryhogan wrote: »
    Hi, Una. 
    I know the current pilot scheme is closed since 2014.
    , but I want to know when is it opening up again? 
    Under EU regulations all demestic meters have to be 2 way by January 2021.
    Is there any update on this meter replacement? 
    Can I request that my meter is put on a "to do now" list as I am wasting money by giving it to the grid for free.
    Kindest regards. 
    Rory
    Dublin 11
    Hi Rory,

    We do not have that information, however the dedicated Home Energy Services team may have an idea.

    Their contact details are towards the end of this page on the Electric Ireland website. The quickest way to speak with them is by telephone or chat.

    Kind regards,
    Una