Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi all! We have been experiencing an issue on site where threads have been missing the latest postings. The platform host Vanilla are working on this issue. A workaround that has been used by some is to navigate back from 1 to 10+ pages to re-sync the thread and this will then show the latest posts. Thanks, Mike.
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Design Certifier Cost

  • 03-02-2021 9:48am
    #1
    Registered Users Posts: 425 ✭✭


    Hi Folks,

    Anyone know how much it costs to get someone to "Design Certify" plans?

    Thanks,


Comments

  • Subscribers Posts: 41,799 ✭✭✭✭sydthebeat


    Hi Folks,

    Anyone know how much it costs to get someone to "Design Certify" plans?

    Thanks,

    Why do you need this?


  • Registered Users Posts: 425 ✭✭billy_beckham


    sydthebeat wrote: »
    Why do you need this?

    We have just received PP, I believe next stage is to get a Design Certifier involved?


  • Subscribers Posts: 41,799 ✭✭✭✭sydthebeat


    We have just received PP, I believe next stage is to get a Design Certifier involved?

    may i ask what you got permission for? a new house?

    'design' and 'assigned' certifers are required if you "opt in" in the BCARs regulations. So first thing to do is to figure out of you want to or not. Do some homework on it.

    in most cases of "opt in" the design and assigned certifiers is the same person and its all included in the one engagement


  • Registered Users Posts: 425 ✭✭billy_beckham


    sydthebeat wrote: »
    may i ask what you got permission for? a new house?

    'design' and 'assigned' certifers are required if you "opt in" in the BCARs regulations. So first thing to do is to figure out of you want to or not. Do some homework on it.

    in most cases of "opt in" the design and assigned certifiers is the same person and its all included in the one engagement

    https://www.irishtimes.com/life-and-style/homes-and-property/should-i-opt-out-of-costly-compliance-paperwork-1.3086373

    Its for a renovation/extension. Reading above it would seem that opting out is not a good idea?

    Typically what does the design/assigned certifier cost?


  • Moderators, Society & Culture Moderators Posts: 39,737 Mod ✭✭✭✭Gumbo


    Hi Folks,

    Anyone know how much it costs to get someone to "Design Certify" plans?

    Thanks,

    Do you have an Assigned Certifier appointed?
    99% of projects, the AC and DC are the same person.


  • Advertisement
  • Registered Users Posts: 425 ✭✭billy_beckham


    Gumbo wrote: »
    Do you have an Assigned Certifier appointed?
    99% of projects, the AC and DC are the same person.

    Is it not Design Certifier first? Then assigned certifier..


  • Subscribers Posts: 41,799 ✭✭✭✭sydthebeat


    Is it not Design Certifier first? Then assigned certifier..

    if they arent the same person... then the assigned certifier may have a serious issue certifying and other persons design.

    thats why they are predominately the same person.

    essentially the design certifier prepares the drawings which are built to... and the assigned certifier certifies that what was build complies with regulation

    what happens if theres a difference of opinion between the design certifier and the assigner certifier of what is compliant or not?

    the vast majority of people opt out as they do not see the value in the extra cost to get certified, especially if they are paying by a mortgage which requires certification anyway, even if that certification is somewhat looser.


  • Registered Users Posts: 425 ✭✭billy_beckham


    sydthebeat wrote: »
    if they arent the same person... then the assigned certifier may have a serious issue certifying and other persons design.

    thats why they are predominately the same person.

    essentially the design certifier prepares the drawings which are built to... and the assigned certifier certifies that what was build complies with regulation

    what happens if theres a difference of opinion between the design certifier and the assigner certifier of what is compliant or not?

    the vast majority of people opt out as they do not see the value in the extra cost to get certified, especially if they are paying by a mortgage which requires certification anyway, even if that certification is somewhat looser.

    Ok, lets assume they are the same person and I'm opting in...how much would it cost?


  • Subscribers Posts: 41,799 ✭✭✭✭sydthebeat


    Ok, lets assume they are the same person and I'm opting in...how much would it cost?

    ive seen typical costs of somewhere around 4-7k for that type of development


  • Registered Users Posts: 425 ✭✭billy_beckham


    sydthebeat wrote: »
    ive seen typical costs of somewhere around 4-7k for that type of development

    Wow, that much!

    Thanks...


  • Advertisement
  • Subscribers Posts: 41,799 ✭✭✭✭sydthebeat


    Wow, that much!

    Thanks...

    if you consider that the person is being asked to "certify", which means to be certain, that every aspect of the build complies to all building regulations, then most professionals will require being on site at least once a week for the duration of the project to satisfy themselves of compliance (once its covered it cane be seen).

    A renovation / extension project could last 20 weeks... and you could be looking at 300-400 min per site visit

    350 x 20 = €7000


  • Moderators, Home & Garden Moderators Posts: 10,141 Mod ✭✭✭✭BryanF


    if you apply the RIAI stages/costs as a % of the build, the DC/AC will be higher than figures suggest above. If you were to comply the requirements of the AD/AC to the letter of the law and ‘lowest common denominator contractor price’ that’s generally accepted, then the certifier will earn every penny of his/her fee. Blame Phil Hogan, and remind your publicly elected rep at every opportunity.


Advertisement