Hardcore fill in excess of 900mm between foundation and FFL

Options
  • 17-02-2024 12:20pm
    #1
    Registered Users Posts: 244 ✭✭


    Hi all,

    We have dugout and poured foundations and we have a nice bit of block work to do to bring it back up to FFL. As far as I'm aware once I pass the need to fill beyond 900m of hardcore I need to look at other options such as suspended concrete floor etc. I have reached out to my engineer and waiting for a reply but wondering has anyone else here ran into this issue in past.