Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

DART+ (DART Expansion)

1227228229230232

Comments

  • Moderators, Science, Health & Environment Moderators Posts: 20,253 Mod ✭✭✭✭Sam Russell


    Would there be a solution to the Howth question if the Dart trains were split from 8 coach to two four coach sets at, say Raheny, with one part heading to Malahide while the second part went to Howth? Perhaps a rework of Howth junction might make it more likely to work.

    Why do they not do more splitting of Dart trains? They run 4 coaches at peak times with passengers crammed in, while empty 8 coach sets will trundle along during low traffic times like early mornings and late evenings when a two coach would do.



  • Registered Users, Registered Users 2 Posts: 15,401 ✭✭✭✭loyatemu


    splitting requires manpower and organisation. I guess it's just a lot easier to send out every train at full length and suck up the additional power costs.

    splitting in-service for the Howth branch is a really terrible idea. One of the key ideas of Dart+ is to improve reliability by operating a very uniform regular service with fixed format trains and minimal conflicting movements. Splitting and reforming has huge potential for introducing delays - IÉ tried it on the Intercity network a few years ago and quickly abandoned it as the process was not reliable. That was a couple of trains a day, not 6 trains an hour!



  • Registered Users, Registered Users 2 Posts: 1,341 ✭✭✭gjim


    The problem is up/down trains have to pass at grade at Howth junction.

    If there was grade separation (never going to happen given cost and complexity), then it would be feasible, for example to send 2 DARTs (out of 12) an hour to Howth, leaving 10 per hour to serve Malahide and north of Malahide.

    But with trains crossing at grade, each slot diverted to Howth would potentially require removing 2 slots from the Malahide/Drogheda service, to retain the same level of separation (and resilience in case of small delays).

    Which would mean reducing the overall capacity of the system from 12 t/h to 10 - a massive waste given the investment involved in DART+ N.



  • Registered Users, Registered Users 2 Posts: 2,949 ✭✭✭Citizen  Six


    You'll then need two drivers. Both trains will be blocking the section while they are split and tested. And the train in rear will have to wait until the train in front has cleared the next section. It's just not feasible



  • Registered Users, Registered Users 2 Posts: 2,949 ✭✭✭Citizen  Six


    The issue people in Howth have is they don't want to have to change trains and wait at Howth Junction. I don't blame them, as it can be fairly rough around there. Irish Rail aren't that great at providing security either.

    But people have been trying to whip up a frenzy about it. With many people claiming the train won't even be running past Howth Junction, and it'll just be a shuttle bus instead.



  • Advertisement
  • Registered Users, Registered Users 2 Posts: 15,401 ✭✭✭✭loyatemu


    I'd expect the HJ-Howth shuttle to be super reliable given that it will just be a couple of 4-car units going back and forth on a line with no other traffic. But I can understand people's reluctance to add a transfer to their journey given the general unreliability of the service that we have all experienced, and the spartan nature of many Dart stations and the terrible passenger information systems. The same applies to Busconnects and people having to change buses - it's a fine idea in principle, but everyone's got plenty of experience of standing around waiting for a bus that never comes.



  • Registered Users, Registered Users 2 Posts: 2,805 ✭✭✭AngryLips


    What a total non-story. I'm glad they went with a standard colour.



  • Moderators, Science, Health & Environment Moderators Posts: 20,253 Mod ✭✭✭✭Sam Russell


    The second driver is only needed to be there during the split. Then there are two trains with each needing its own driver.

    They do this a lot in the UK system. It works for them - do they have a different type of train? Are the Dart trains not designed for splitting while in service?



  • Registered Users, Registered Users 2 Posts: 9,934 ✭✭✭cgcsb


    DART+ N is an infrastructure project. It won't remove the physical infrastructure allowing for howth to city centre trains. IÉ do not need planning permission to change service patterns so it's not really anything for abp to consider. The residents may seek a JR and whether they get one or not will be telling since the issue is imaginary.



  • Registered Users, Registered Users 2 Posts: 15,401 ✭✭✭✭loyatemu




  • Advertisement
  • Registered Users, Registered Users 2 Posts: 254 ✭✭Thunder87


    JR's are frequently taken for reasons completely unrelated to the actual grievance people have though. The usual way it works with JR's on housing is NIMBYs don't want extra traffic/disruption/whatever but will hire someone to find a technicality around environmental surveys or some directive that wasn't followed to the letter. So the fact they have a grievance in the first place is a good indicator they'll at least try their hand at a JR



  • Registered Users, Registered Users 2 Posts: 7,826 ✭✭✭GerardKeating


    The do this (or did maybe) with Galway/Mayo trains. More suited for long distance, where the time to split is a small fraction of the total journey time.



  • Registered Users, Registered Users 2 Posts: 231 ✭✭PlatformNine


    ah I never really considered that. I think they are still going to try and challenge it with another path, but even then based on their complaints nothing they are objecting to is infrastructure related.

    I imagine though they will still find a way to protest the changes, as to how they will do that or if it will even work, I am not sure, but they will find a way.



  • Registered Users, Registered Users 2 Posts: 9,934 ✭✭✭cgcsb


    As an aside, I read the luas finglas RO application. It's a very high quality set of documents. Hopefully this is a new standard for public projects which will be much more robust against court action.

    In contrast, the DART+ West documents were littered with typos, poor sentence structure, wrong document references and figure references etc. A playground for solicitor really.



  • Registered Users, Registered Users 2 Posts: 6 Seamie123


    As a Dublin Bay North constituent, all the major candidates' leaflets I saw mentioned opposition to the removal of direct DARTs to Howth, including the Green Party candidate. The objectors will have plenty of political clout behind them when the time comes.



  • Registered Users, Registered Users 2 Posts: 18,524 ✭✭✭✭LXFlyer


    They tend not to do joining/splitting in the UK on a two track railway blocking the running lines though as doing it at Raheny would. It’s usually at stations where they can be overtaken and not risking causing a blockage, and would block the line until the signal section is cleared.

    It really isn’t an option. Changing to a shuttle is a much more efficient approach - it’s just going to need a similar approach as that at Broombridge to make Howth Junction a location that people feel safe to change at.

    People tend not to visualise the more frequent services that would be running and look at it in the here and now. Twenty years ago could anyone imagine Broombridge being somewhere that people would be using as an interchange - that’s the change in mindset that’s needed in this case.

    Plus people changing from the shuttle need assurances that they will be able to get on the connecting DART to city - maximising connections with Clongriffin starters would be key at peak times.

    Incidentally, I seem to recall that you have raised this several times here over the years, and I’m pretty sure that I explained that they did make a significant effort at splitting and joining trains during the day at Connolly and Bray back when the economy tanked, but that my understanding was that the whole process actually didn’t save money after all, due in part to the additional driver resources needed to do the shunting back and forth of units to/from Fairview and the constant switching around in Bray which proved challenging to say the least!

    The lack of any facilities to stable trains at the northern ends of the DART lines (or easily in the case of Malahide) doesn’t help either. It restricts the option to Connolly and Bray which makes the whole operation that bit trickier.

    Sometimes it’s just easier and more cost effective to keep the capacity in service given the infrastructure constraints and to keep the drivers on revenue earning services.



  • Registered Users, Registered Users 2 Posts: 144 ✭✭DoctorPan


    And thus no surprise when Irish Rail decided to bring Atkins in to take over it, such was the dissatisfaction with the product IDOM and ROD provided to them.



  • Registered Users, Registered Users 2 Posts: 218 ✭✭scrabtom


    So ROD and IDOM did the Dart Plus applications but Atkins are going to do future planning applications for them?

    Good news if so, if the Dart Plus applications were substandard.



  • Registered Users, Registered Users 2 Posts: 226 ✭✭Bsharp


    Atkins won a competitive tendering process to take on the next stage of the work. There were lots of other bidders. IDOM, ROD and others were also appointed to the same client side framework so are likely to have future involvement still.



  • Moderators, Science, Health & Environment Moderators Posts: 5,267 Mod ✭✭✭✭spacetweek


    Happy new year all.
    Can I ask what IDOM and ROD stand for?



  • Advertisement
  • Registered Users, Registered Users 2 Posts: 2,174 ✭✭✭KrisW1001


    They’re two private engineering companies. IDOM is a Spanish company, (Ingeniería y Dirección de Obras y Montaje, “Engineering, Construction Management, Installation”), ROD is Irish (Roughan - O'Donovan)



  • Registered Users, Registered Users 2 Posts: 9,934 ✭✭✭cgcsb


    Update, the facts:

    The option to take a JR against DART+ Southwest has now expired and DART+SW now has an operable railway order and may now proceed to tender for works, pending final funding approval from the NTA/DoT. Expect to see some tenders this year, perhaps even tender review/award by year end.

    DART+W is in the JR process. ABP were to submit it's case to the court in early December but have failed to do so, they have indicated that they will be unable to do so until the end of January. If that is met the case can proceed around the end of February. Hopefully this will be concluded swiftly.

    We could even see some early works on both projects in 2025 to prepare for the main works. Main construction is now highly likely to get started in 2026 and really ramp up in 2027. There is no final construction programme yet given the variables but a completion date of 2031 is possible.

    The Elephant:

    Depot-gate. The DART+ scheme may be built but completely inoperable without a Depot, a revised RO application for the Depot is unlikely in 2025. This is a major challenge, if the application can be made in 2026, experience tells us that ROs take 2 years, meaning 2028 before a decision. Tendering and constructing the Depot in time for completion of the rest of the scheme seems unlikely at this point. However reforms to ABP and the planning courts may relieve some of these issues, it's a wait and see scenario.



  • Moderators, Computer Games Moderators, Recreation & Hobbies Moderators Posts: 10,631 Mod ✭✭✭✭CatInABox


    Thanks for the update, good to know where things stand.

    I think that you might be overly pessimistic on the RO for the depot though, I doubt that it would take two years. It is solely going to be a depot, and bar the tie in works, will have nothing else. It can't take two years to look over just a depot.



  • Registered Users, Registered Users 2 Posts: 71,849 ✭✭✭✭L1011


    If the depot is moved, there is still a need for a further application for West of Maynooth, as the RO was cut off at Bond Bridge, just beyond the station.

    Kilcock extension is meant to be in design currently and will presumably handle that, but if not, they may need to do a basic planning app for the electrification and maybe some additional turnback sidings.



  • Registered Users, Registered Users 2 Posts: 254 ✭✭Thunder87


    Bog standard housing applications in the middle of a housing crisis are frequently taking 2+ years for a decision from ABP, it shouldn't take that long but still definitely a possibility unless they finally start getting their house in order this year.

    Has there been any word on what disruption there'll be to services during the construction? Just thinking whether construction will need to be staggered so as not to clash with any adjacent BusConnects routes



  • Registered Users, Registered Users 2 Posts: 2,058 ✭✭✭Economics101


    In the case of strategic infrastructure like most transport projects, the Government should have the power to direct ABP to move such projects up the queue. ABP can of course still act independenty when making a judgment.

    Alos once the ABP backog is substantially alleviated, there should be a new rule: if ABP does not give a verdict within 6 months, then planning consent can be assumed. Put a gun to their heads.



  • Moderators, Computer Games Moderators, Recreation & Hobbies Moderators Posts: 10,631 Mod ✭✭✭✭CatInABox


    ABP already has an infrastructure department to handle these kinds of things, so I think it's already prioritised. Perhaps not to the extent we would all like, but it is.

    On that rule, that's a sure fire way of getting JRed, and almost certainly successfully at that.



  • Moderators, Sports Moderators Posts: 12,635 Mod ✭✭✭✭Cookiemunster


    ABP was hugely understaffed at the time and got hit with a barrage of SHDs. Then you had the scandal with the board.

    All these issues have been resolved now though. They are fully staffed, have a reconstituted board and are moving new cases through the system pretty much within the required timescales.



  • Registered Users, Registered Users 2 Posts: 9,934 ✭✭✭cgcsb


    A planning amnesty right now seems like a great idea, assuming the legals can deal with it. I would advocated any infrastructure project and and any urban housing scheme over 100 units be granted for the next few years until our situation stabilises.



  • Advertisement
  • Registered Users, Registered Users 2 Posts: 9,934 ✭✭✭cgcsb


    They're getting JRs anyway so saving 2 years by cutting out the middle man could be the ticket to clear a backlog



  • Registered Users, Registered Users 2 Posts: 9,934 ✭✭✭cgcsb


    What projects are moving along within their required time scales? The 6 month mark has long past on all such projects AFAIK.

    The Luas Fingls application went in November, due to be decided 26th of May 2025. Luas Finglas is also a very good quality submission. I'll eat my hat if it has an RO by that date.



  • Registered Users, Registered Users 2 Posts: 1,339 ✭✭✭pigtown


    That's leaving the state wide open to issues down the line, from substandard designs, to possible drainage and flooding issues, to unsafe roads. It would be like signing a blank check for future court cases by those affected.

    It's probably also against EU law given the environmental impact of projects on European sites in particular wouldn't be assessed.



  • Moderators, Sports Moderators Posts: 12,635 Mod ✭✭✭✭Cookiemunster


    I said new cases are progressing relatively quickly. I didn't mention those in the backlog. Those are also now starting to move, but as they've been there for so long already it doesn't really make a noticeable difference to their timelines.

    Christ no. That would just lead to massive problems down the line. And it would be highly unlikely to be legal anyway.



  • Registered Users, Registered Users 2 Posts: 9,934 ✭✭✭cgcsb


    We'll see with luas finglas then since that's newly submitted. Here's hoping it gets an RO in May but I have my doubts



  • Moderators, Sports Moderators Posts: 12,635 Mod ✭✭✭✭Cookiemunster


    I think you need to read the post I was replying to.



  • Advertisement
  • Registered Users, Registered Users 2 Posts: 2,058 ✭✭✭Economics101


    Just to be clear, a planning amnesty is not anything which I would ever support. Properly legislated changes to general rules are a different matter.



  • Registered Users, Registered Users 2 Posts: 18,402 ✭✭✭✭Idbatterim


    question, if there was just a shuttle to howth, how many darts could serve the airport an hour? 2 each way or just 1 ? also they have mentioned this plan before, would it be single or twin track?



  • Registered Users, Registered Users 2 Posts: 231 ✭✭PlatformNine


    While I don't want to underestimate the problems the delayed depot might bring, I think its a bit pessimistic to say that the depot issues might make D+ completely inoperable. There is no denying the delays it might cause, but given the time it takes the electrify it was going to take quite a bit of time to get the full capacity D+ network anyways.

    With the third order soon to be in place, there will "only" be 93 units left in the framework, or 5 orders(assuming 20 units per order) if they decide to fulfill the entire framework. I don't like to use the word only, as that is still almost two-thirds of the framework, but it isn't a doomed timeframe. If they place the fourth order sometime in 2027 and then place an order ever year after until 2031 when the framework expires, they can still complete the framework.

    Its far from the ideal situation to be in, and I think its likely that at the current rate when the D+ network first opens they may be short units to operate at fully capacity. But I think any shortage of units we might see would be temporary while they are still being manufactured or commissioned. As Jim Meade put it, It's "not on a critical path" yet. That I do think if they take too long to get a new depot designed, or if it gets stuck in ABP or JR hell, then there might be problem, but I am trying not to think about that.

    Also, what is the story with the D+W JRs? The court cases appear to be up on the high court website but there has been no publicity about it's a bit hard to find out what is going on. I'm assuming it's about the Ashtown crossing?



  • Registered Users, Registered Users 2 Posts: 14,951 ✭✭✭✭Thelonious Monk


    so depressing we just can't do anything in this country



  • Registered Users, Registered Users 2 Posts: 2,392 ✭✭✭VonLuck


    Is this set in stone or is there any chance this timeline could improve?



  • Advertisement
  • Registered Users, Registered Users 2 Posts: 14,951 ✭✭✭✭Thelonious Monk


    The timeline will most likely get worse, it's ireland after all



  • Registered Users, Registered Users 2 Posts: 153 ✭✭VeryOwl


    Everything has been said already but a vague date of 2027 to begin construction really is frightfully poor.

    We've been talking about "DART+" / "DART Expansion" for a decade now and absolutely nothing has been delivered.

    It's shameful that at this rate none of the proposed network expansions below will have even begun construction by the time the gates were meant to open. Is there any legitimate reason why preparing the tenders etc. is going to take 2-3 years?



  • Registered Users, Registered Users 2 Posts: 2,570 ✭✭✭Glaceon


    At this rate I wouldn’t be surprised if the batteries in the BEMUs go end of life before Drogheda is electrified! 😂



  • Registered Users, Registered Users 2 Posts: 30,257 ✭✭✭✭blanch152


    Didn't someone say that the opportunity for JR of DART+ SouthWest had expired, which means it has moved ahead of Dart West?



  • Registered Users, Registered Users 2 Posts: 231 ✭✭PlatformNine


    If I am reading the timeline right, the 2-3 year timeline is for the main works, but there are plenty of enabling works to be done before then. So it isn't 2-3 years of no work being done, but maybe a year of no work because of tendering, then enabling works begin, and then by the time the enabling works finish, the main works contract should be awarded and ready to begin.



  • Registered Users, Registered Users 2 Posts: 9,934 ✭✭✭cgcsb


    yes techincally they are ahead but likely both will be delivered together



  • Registered Users, Registered Users 2 Posts: 9,934 ✭✭✭cgcsb


    This was expected. Irish Rail can deliver parts of the works themselves before getting a contractor to site in 2027. The arrival of main contractors on site in 2027 will be more of a ramp up of works.



  • Registered Users, Registered Users 2 Posts: 263 ✭✭Montys return


    Does anyone know what the increase in capacity for the northern line will be from current service level to when the BEMUs are running from 2026?

    I see the attached info graphic mentions that the increases in capacity are a comparison between post BEMU and the service level upon completion of Dart + Coastal North.

    Will there actually be a significant increase in passenger capacity at peak when the BEMUs are rolled out?



  • Moderators, Category Moderators, Arts Moderators, Entertainment Moderators, Technology & Internet Moderators Posts: 22,698 CMod ✭✭✭✭Sad Professor


    I can't find it now but Irish Rail was asked about this recently. I think the short answer was not really. They said total capacity of the BEMUs will be about the same as the current commuter trains but a bit more than the inter-city trains which they will be replacing entirely on the northern line.



  • Registered Users, Registered Users 2 Posts: 18,524 ✭✭✭✭LXFlyer


    The BEMUs will be direct replacements for the 29000s.

    No frequency increase until the EMUs arrive and electrification happens.



  • Advertisement
Advertisement